Friday, April 26, 2013

Blalock Not Working Saturday, April 27, Due to Weather Conditions

April 26, 2013 - The contractor, Charles Blalock & Sons, will not be working on Saturday, April 27.  In anticipation of the inclement weather predicted for Saturday, Blalock worked during the early morning hours of Thursday, April 25, and continues to make preparations for critical tie-in work to be performed this Sunday, April 28.  Placing the new line in service will allow Blalock to begin work on the water and gas line replacements in Zone 1 on Monday morning, April 29.  As has been the case since construction began, there will be two crews on the job to ensure that work stays on schedule.  Also scheduled for Monday, Pipeline Constrution Company will be conducting a one-day test bore beneath the golf cart tunnel in front of Cherokee Country Club to confirm sub-surface conditions. 