The schedule will be as follows:
Thursday, June 27, to Sunday morning, June 30, 8 a.m.
Access to CCC north side facilities from Kingston Pike ONLY
Sunday morning, June 30, 8 a.m., to Wednesday evening, July 3, 5 p.m.
Access to CCC north side facilities from Northshore Drive ONLY
Wednesday evening, July 3, 5 p.m., to Final Project Completion
Access to CCC north side facilities from Kingston Pike ONLY
Access to the CCC facilties on the south side of Lyons View Pike is unaffected, and will remain from Kingston Pike ONLY for the remainder of the project.
The construction contractors will not be working Thursday, July 4, through Sunday, July 7, and will resume activity on Monday, July 8. At that time, Zone 3 activity on the sewer and gas line replacements will be nearing completion, and preparations will begin for transitioning into Zone 4.
Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Completion of the project is scheduled for November, 2013, prior to Thanksgiving.
View Construction Progress Map Zone 3 (effective until 8 a.m., Sunday, June 30).
View Construction Progress Map Zone 3 (effective after 8 a.m., Sunday, June 30).
Construction activity and road barricade in Zone 3 west of Cherokee Country Club (from Kingston Pike).
Construction activity and road barricade from west end of project (from Northshore Drive).