July 12, 2013 UPDATE -
Work on the far western end of Zone 3 is wrapping up as existing gas
services are being tied over to the new gas main. Installation of the
new water main within Zone 4 continues. Once the disinfection and
flushing process is complete on the new water main, the contractor will
begin tying water services over to the new water main. Customers will be
notified in advance of the brief interruption of water service as the
individual services are transferred to the new main. As soon as all
water main replacement work in Zone 4 is complete, Blalock will begin
work to replace the existing sewer and gas lines within Zone 4.
Note: The contractor will not be
working this Saturday & Sunday, July 13-14. The disinfection
process on the recently installed water line in Zone 4 is underway and
will not be ready for confirmatory sample collection and testing until
Monday morning, July 15. Work on other utilities in the area can't be
started until the new water line is in service, and the old water line
is removed, to make room for the other new utilities.
Reminder: Access to all Cherokee
Country Club (CCC) facilities is only available from Kingston Pike.
Access to CCC from Northshore Drive will not be available until the
project is completed.
Lyons View Pike remains closed to through traffic
between Lakeshore Park on the west end and Colony Way on the east end.
Harley Drive remains barricaded at the Lyons View Pike intersection for
the duration of this project. Completion of the project is scheduled for
November, 2013, prior to Thanksgiving.
Zone 4 Water Line Installation
Installing an isolation valve on existing 1915 6" Cast Iron Water Line