July 26, 2013 Update - All work
in Zone 4 has been completed, and Blalock has now transitioned into Zone 5.
Within Zone 5, the trench that will contain the new utility lines will
transition from the north lane (westbound) to the south lane (eastbound) in the
vicinity of 5628 Lyons View Pike. In general, as placement of the new lines
within the trench is completed and the trench is backfilled, access to
individual driveways within Zone 5 will shift from Northshore Drive to Kingston
Pike as the trench work moves past each driveway.
Blalock has also begun working simultaneously in Lyons
Pointe Lane immediately to the east of Lyons View Pike. This work only affects
those residents that live along Lyons Pointe Lane.
Reminder: Access to all Cherokee Country
Club (CCC) facilities is only available from Kingston Pike. Access to CCC from
Northshore Drive will not be available until the project is completed.
Lyons View Pike remains closed to through traffic between
Lakeshore Park on the west end and Colony Way on the east end. Harley Drive
remains barricaded at the Lyons View Pike intersection for the duration of this
project.
Schedule Note: Although the weather has
been unusually wet through much of the project, the contractor has made good use
of the extended work hours, longer work week and multiple crews to make
excellent progress. As such, KUB is presently evaluating the remaining work and
coordinating with the contractor and the City to revise the anticipated
completion date. After the pipeline work is finished, the City's contractor will
complete the final paving of the road. Stay tuned to future updates for a
revised schedule on reopening Lyons View Pike to through traffic.
Preparing to mill the existing pavement in the eastbound lane
Common trench will contain new water, natural gas, and sewer for main pipes