Friday, August 16, 2013

Lyons View Pike Project Update

August 16, 2013 - Work began in Zone 6 on Tuesday, August 13. Zone 6 is a relatively short zone and work is expected to move quickly. As such, placement of temporary pavement in Zone 6 is expected to occur before the end of August. The Construction Map has been updated to reflect the current progress. All utility work impacting Lyons View Pike is expected to be complete by mid-September with the City's resurfacing work to follow immediately afterwards. Weather permitting, it's expected that the roadway will be open to traffic by the end of September, however construction activity will still be occurring outside of the roadway and motorists will need to use caution when traveling through the area.

Work also continues in the Lyons Pointe Lane area east of Lyons View Pike. KUB is also continuing its preparations for tree pruning and vegetation removal related to the overhead electric circuit along Lyons View Pike.

Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project.

View Current Construction Progress Map for Zone 6


Construction Zone 6



Intersection of Lyons View Pike and Oak Grove Lane



Blalock's Superintendent inspecting 6" sewer force main tie-in at Oak Grove Lane





2 comments:

  1. Greetings! Very useful advice in this particular article! It’s the little changes which will make the greatest changes. Thanks a lot for sharing!|

    Construction Material Testing
    Architecture Urban Planning
    Project Management Consultancy

    ReplyDelete
  2. usefull project
    pennsylvania.quantity-takeoff.com




    ReplyDelete