August 8, 2013 - Work in Zone 5 is nearing completion, with water and natural gas services being tied over to the newly installed mains. Placement of temporary pavement within Zone 5 is tentatively scheduled for Monday, August 12, weather permitting. Transition into Construction Zone 6 is set to begin Tuesday, August 13. Work in the Lyons Pointe Lane area just to the east of Lyons View Pike continues. The Construction Map has been updated to reflect the Zone 5 progress. While not directly related to the ongoing multiple utility upgrade project along Lyons View Pike, KUB is also scheduling tree pruning and vegetation removal work in the area at this time to coincide with the road closure so that the impact to customers is held to a minimum.
NOTE: The contractor will not be working this Saturday and Sunday, August 10-11. Due to the pending transition from one work zone to the next, utility installation work in Zone 6 can’t be started until temporary paving work has been completed in Zone 5.
Schedule Note: Construction continues to progress well ahead of schedule. At the current rate and weather permitting, it is possible that all construction work and final paving within Lyons View Pike can be completed in September. KUB continues to work closely with the contractor and the City of Knoxville to refine the construction schedule in order to firm up plans for the reopening of the roadway.
View Current Construction Progress Map for Zone 5
Thursday, August 8, 2013
Friday, August 2, 2013
Lyons View Pike Multiple Project Update
August 2, 2013 - Work continues to progress well within Zone 5 and along Lyons Pointe Lane. As soon as the disinfection and flushing processes are completed for the new water main on Lyons Pointe Lane, water services will be connected over to the new water main. Please continue to consult this blog on a regular basis as the Construction Progress Map will be updated frequently to track shifts in the full road closure area within Zone 5.
Schedule Note: At the current rate, KUB anticipates the project will be completed several weeks in advance of the original November time frame. We continue to work with the contractor and the City of Knoxville to further refine the original project completion date.
View Current Construction Progress Map for Zone 5
Backfilled trench in Zone 5
Fusing 50' sections of High Density Polyethylene sewer pipe
Schedule Note: At the current rate, KUB anticipates the project will be completed several weeks in advance of the original November time frame. We continue to work with the contractor and the City of Knoxville to further refine the original project completion date.
View Current Construction Progress Map for Zone 5
Backfilled trench in Zone 5
Fusing 50' sections of High Density Polyethylene sewer pipe
Thursday, August 1, 2013
Lyons View Project Update
July 31, 2013 Update – Construction Zone 5 Map updated. Please continue to consult this blog on a regular basis as the Construction Progress Map will be updated frequently to track shifts in the full road closure area within Zone 5.
View Current Construction Progress Map for Zone 5
View Current Construction Progress Map for Zone 5
Friday, July 26, 2013
Lyons View Project Update
July 26, 2013 Update - All work
in Zone 4 has been completed, and Blalock has now transitioned into Zone 5.
Within Zone 5, the trench that will contain the new utility lines will
transition from the north lane (westbound) to the south lane (eastbound) in the
vicinity of 5628 Lyons View Pike. In general, as placement of the new lines
within the trench is completed and the trench is backfilled, access to
individual driveways within Zone 5 will shift from Northshore Drive to Kingston
Pike as the trench work moves past each driveway.
Blalock has also begun working simultaneously in Lyons
Pointe Lane immediately to the east of Lyons View Pike. This work only affects
those residents that live along Lyons Pointe Lane.
Reminder: Access to all Cherokee Country
Club (CCC) facilities is only available from Kingston Pike. Access to CCC from
Northshore Drive will not be available until the project is completed.
Lyons View Pike remains closed to through traffic between
Lakeshore Park on the west end and Colony Way on the east end. Harley Drive
remains barricaded at the Lyons View Pike intersection for the duration of this
project.
Schedule Note: Although the weather has
been unusually wet through much of the project, the contractor has made good use
of the extended work hours, longer work week and multiple crews to make
excellent progress. As such, KUB is presently evaluating the remaining work and
coordinating with the contractor and the City to revise the anticipated
completion date. After the pipeline work is finished, the City's contractor will
complete the final paving of the road. Stay tuned to future updates for a
revised schedule on reopening Lyons View Pike to through traffic.
Preparing to mill the existing pavement in the eastbound lane
Common trench will contain new water, natural gas, and sewer for main pipes
Thursday, July 18, 2013
Lyons View Pike Project Update
July 18, 2013 Update - Work in Zone 3 has been completed. All traffic from address 5412 Lyons View Pike east must access from Kingston Pike. Blalock has completed the water main installation in Zone 4 and tied over all service lines. Work continues in Zone 4 to install the new sewer and natural gas mains. Barring any unforeseen construction issues, and weather permitting, Blalock expects to transition from Zone 4 to Zone 5 by next week.
Reminder: Access to all Cherokee Country Club (CCC) facilities is only available from Kingston Pike. Access to CCC from Northshore Drive will not be available until the project is completed.
Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Completion of the project is scheduled for November, 2013, prior to Thanksgiving.
View Current Construction Progress Map for Zone 4
Reminder: Access to all Cherokee Country Club (CCC) facilities is only available from Kingston Pike. Access to CCC from Northshore Drive will not be available until the project is completed.
Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Completion of the project is scheduled for November, 2013, prior to Thanksgiving.
View Current Construction Progress Map for Zone 4
Friday, July 12, 2013
Lyons View Pike Project Update
July 12, 2013 UPDATE -
Work on the far western end of Zone 3 is wrapping up as existing gas
services are being tied over to the new gas main. Installation of the
new water main within Zone 4 continues. Once the disinfection and
flushing process is complete on the new water main, the contractor will
begin tying water services over to the new water main. Customers will be
notified in advance of the brief interruption of water service as the
individual services are transferred to the new main. As soon as all
water main replacement work in Zone 4 is complete, Blalock will begin
work to replace the existing sewer and gas lines within Zone 4.
Note: The contractor will not be
working this Saturday & Sunday, July 13-14. The disinfection
process on the recently installed water line in Zone 4 is underway and
will not be ready for confirmatory sample collection and testing until
Monday morning, July 15. Work on other utilities in the area can't be
started until the new water line is in service, and the old water line
is removed, to make room for the other new utilities.
Reminder: Access to all Cherokee
Country Club (CCC) facilities is only available from Kingston Pike.
Access to CCC from Northshore Drive will not be available until the
project is completed.
Lyons View Pike remains closed to through traffic
between Lakeshore Park on the west end and Colony Way on the east end.
Harley Drive remains barricaded at the Lyons View Pike intersection for
the duration of this project. Completion of the project is scheduled for
November, 2013, prior to Thanksgiving.
Zone 4 Water Line Installation
Installing an isolation valve on existing 1915 6" Cast Iron Water Line
Wednesday, July 3, 2013
Lyons View Pike Project Update
July 3, 2013 UPDATE - Work in Zone 3 is nearing completion. By 3 p.m., Wednesday, July 3, placement of temporary pavement within the majority of Zone 3 will be complete. Blalock & Sons will adjust traffic control devices at 3 p.m. Wednesday such that all Cherokee Country Club (CCC) traffic must enter from and exit to Kingston Pike. After 3 p.m. Wednesday, July 3, all CCC facilities will not be accessible from Northshore Drive for the remainder of the project.
The construction contractors will not be working Thursday, July 4, through Sunday, July 7, and will resume activity on Monday, July 8. At that time, the remaining work on the western-most end of Zone 3 will continue, and preparation work for the new water line construction within Zone 4 will commence.
Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Completion of the project is scheduled for November, 2013, prior to Thanksgiving.
View Construction Progress Map Zone 4 (effective after 3 p.m., Wednesday, July 3)
The construction contractors will not be working Thursday, July 4, through Sunday, July 7, and will resume activity on Monday, July 8. At that time, the remaining work on the western-most end of Zone 3 will continue, and preparation work for the new water line construction within Zone 4 will commence.
Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Completion of the project is scheduled for November, 2013, prior to Thanksgiving.
View Construction Progress Map Zone 4 (effective after 3 p.m., Wednesday, July 3)
Subscribe to:
Posts (Atom)


