Wednesday, September 25, 2013
Friday, September 20, 2013
Lyons View Pike Project Update
September 20, 2013 UPDATE - The
City of Knoxville has completed all milling, paving, and striping work, all
traffic control measures have been removed, and the entire stretch of Lyons View
Pike has now been reopened to through traffic.
Lyons View Pike has been closed to through traffic since
April 15, 2013, in conjunction with KUB’s multiple utility upgrade project to
replace the natural gas, water, and wastewater mains in this area.
KUB’s contractor, Charles Blalock & Sons, and their
subcontractor, Pipeline Construction, completed all utility installation work in
early September, nearly two months ahead of schedule. All totaled, Charles
Blalock & Sons and Pipeline Construction replaced 20,222 feet, or 3.83
miles, of utility pipe over a 21 week period.
KUB would like to extend its sincere appreciation to
residents and businesses in the Lyons View Pike area, as well as commuters who
frequently travel this busy stretch of roadway, for their patience and
understanding during the past several months as we completed this challenging
project.
Friday, September 13, 2013
Lyons View Pike Project Update
September 13, 2013 UPDATE -
KUB’s contractor, Charles Blalock & Sons, and their subcontractor, Pipeline
Construction, have completed installation of all natural gas, water, and
wastewater pipes and related equipment along the 1.5 mile Lyons View Pike
construction zone and adjacent areas nearly two months ahead of schedule.
With utility upgrades completed, the work zone has now
been turned over to the City of Knoxville for roadway resurfacing work. The
City’s paving contractor is scheduled to begin milling, final paving, and
striping work along Lyons View Pike on Monday, September 16. The roadway
reopening date will be determined by completion of the City’s paving work.
Lyons View Pike remains closed to through traffic between
Lakeshore Park on the west end and Colony Way on the east end. Harley Drive
remains barricaded at the Lyons View Pike intersection for the duration of this
project.
Due to changing roadway surface conditions, and the
ongoing presence of large trucks and heavy equipment, motorists should continue
to proceed with caution when traveling anywhere within the area.
Thursday, September 5, 2013
Lyons View Pike Project Update
September 5, 2013 UPDATE - With utility related work in Lyons View Pike nearing completion, the City of Knoxville's paving contractor is scheduled to perform milling, paving, and striping of the roadway beginning the week of September 16. Prior to that, KUB's contractor will be making final tie-ins of the force mains and completing final "punch-list" items at various locations throughout the length of the project. In addition, Lyons Pointe Lane and areas adjacent to its intersection with Lyons View Pike will be paved by KUB's contractor and all remaining vegetation management work will be completed. Due to the rapidly changing nature and location of the work needed to close out construction and prepare for final paving, motorists should continue to use caution when traveling anywhere within the project area.
Weather permitting, it's expected the City's contractor will complete the resurfacing work and the roadway will re-open to through traffic sometime the week of September 23.
The Construction Progress Map for Zone 7 remains unchanged. Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project.
View Current Construction Progress Map.
Pipeline Construction installing 8" polyethylene sewer force main adjacent to Lakeshore Park
Preparing to thermally fuse 6" sewer force main
Fusing 6" sewer force main
Tree pruning underway along overhead electric circuit
Re-sodding staging area in Lakeshore Park
Weather permitting, it's expected the City's contractor will complete the resurfacing work and the roadway will re-open to through traffic sometime the week of September 23.
The Construction Progress Map for Zone 7 remains unchanged. Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project.
View Current Construction Progress Map.
Pipeline Construction installing 8" polyethylene sewer force main adjacent to Lakeshore Park
Preparing to thermally fuse 6" sewer force main
Fusing 6" sewer force main
Tree pruning underway along overhead electric circuit
Re-sodding staging area in Lakeshore Park
Thursday, August 29, 2013
Lyons View Pike Project Update
August 29, 2013 UPDATE - Work continues in Construction Zone 7, immediately southeast of Lyons View Pike. As part of this work, construction equipment is partially extending into Lyons View Pike just east of the Oak Grove Lane intersection on the far western end of the project. Tree pruning and vegetation removal work continues at various locations along the entire length of Lyons View Pike. Motorists should continue to use caution when traveling through the entire area.
The Construction Progress Map for Zone 7 remains unchanged. Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project.
All utility work impacting Lyons View Pike is expected to be complete by mid-September with the City's resurfacing work to follow immediately afterwards. Weather permitting, it's expected that the roadway will be open to traffic by the end of September.
View Current Construction Progress Map for Zone 7
Contractor set up to bore 6" sewer main through Lakeshore Park
The Construction Progress Map for Zone 7 remains unchanged. Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project.
All utility work impacting Lyons View Pike is expected to be complete by mid-September with the City's resurfacing work to follow immediately afterwards. Weather permitting, it's expected that the roadway will be open to traffic by the end of September.
View Current Construction Progress Map for Zone 7
Contractor set up to bore 6" sewer main through Lakeshore Park
Friday, August 23, 2013
Lyons View Pike Project Update
August 23, 2013 - Work in
Construction Zone 6 was completed on Thursday, August 22, with the placement of
temporary pavement and general cleanup within the zone. Work in Zone 7 has
already begun and will continue for approximately the next three weeks. Zone 7
is immediately southeast of Lyons View Pike and along the north boundary of
Lakeshore Park. Installation of two new sewer mains in Zone 7 will require that
construction equipment be located in Lyons View Pike for most of the next three
weeks. Tree pruning and vegetation removal work continues along the entire route
of Lyons View Pike. Motorists should continue to use caution when traveling
through the area.
Traffic Note: Effective Friday,
August 23, the full road closure area will be located as shown on the updated
Construction Progress Map for Zone 7. The road closure will remain at that
location for the remainder of the project. All residences and businesses located
west of the closure area will be accessible from Northshore Drive only. Those
located east of the closure area will remain accessible from Kingston Pike
only.
Lyons View Pike remains closed to through traffic between
Lakeshore Park on the west end and Colony Way on the east end. Harley Drive
remains barricaded at the Lyons View Pike intersection for the duration of this
project.
Friday, August 16, 2013
Lyons View Pike Project Update
August 16, 2013 - Work began in Zone 6 on Tuesday, August 13. Zone 6 is a relatively short zone and work is expected to move quickly. As such, placement of temporary pavement in Zone 6 is expected to occur before the end of August. The Construction Map has been updated to reflect the current progress. All utility work impacting Lyons View Pike is expected to be complete by mid-September with the City's resurfacing work to follow immediately afterwards. Weather permitting, it's expected that the roadway will be open to traffic by the end of September, however construction activity will still be occurring outside of the roadway and motorists will need to use caution when traveling through the area.
Work also continues in the Lyons Pointe Lane area east of Lyons View Pike. KUB is also continuing its preparations for tree pruning and vegetation removal related to the overhead electric circuit along Lyons View Pike.
Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project.
View Current Construction Progress Map for Zone 6
Construction Zone 6
Intersection of Lyons View Pike and Oak Grove Lane
Blalock's Superintendent inspecting 6" sewer force main tie-in at Oak Grove Lane
Work also continues in the Lyons Pointe Lane area east of Lyons View Pike. KUB is also continuing its preparations for tree pruning and vegetation removal related to the overhead electric circuit along Lyons View Pike.
Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project.
View Current Construction Progress Map for Zone 6
Construction Zone 6
Intersection of Lyons View Pike and Oak Grove Lane
Blalock's Superintendent inspecting 6" sewer force main tie-in at Oak Grove Lane
Thursday, August 8, 2013
Lyons View Pike Project Update
August 8, 2013 - Work in Zone 5 is nearing completion, with water and natural gas services being tied over to the newly installed mains. Placement of temporary pavement within Zone 5 is tentatively scheduled for Monday, August 12, weather permitting. Transition into Construction Zone 6 is set to begin Tuesday, August 13. Work in the Lyons Pointe Lane area just to the east of Lyons View Pike continues. The Construction Map has been updated to reflect the Zone 5 progress. While not directly related to the ongoing multiple utility upgrade project along Lyons View Pike, KUB is also scheduling tree pruning and vegetation removal work in the area at this time to coincide with the road closure so that the impact to customers is held to a minimum.
NOTE: The contractor will not be working this Saturday and Sunday, August 10-11. Due to the pending transition from one work zone to the next, utility installation work in Zone 6 can’t be started until temporary paving work has been completed in Zone 5.
Schedule Note: Construction continues to progress well ahead of schedule. At the current rate and weather permitting, it is possible that all construction work and final paving within Lyons View Pike can be completed in September. KUB continues to work closely with the contractor and the City of Knoxville to refine the construction schedule in order to firm up plans for the reopening of the roadway.
View Current Construction Progress Map for Zone 5
NOTE: The contractor will not be working this Saturday and Sunday, August 10-11. Due to the pending transition from one work zone to the next, utility installation work in Zone 6 can’t be started until temporary paving work has been completed in Zone 5.
Schedule Note: Construction continues to progress well ahead of schedule. At the current rate and weather permitting, it is possible that all construction work and final paving within Lyons View Pike can be completed in September. KUB continues to work closely with the contractor and the City of Knoxville to refine the construction schedule in order to firm up plans for the reopening of the roadway.
View Current Construction Progress Map for Zone 5
Friday, August 2, 2013
Lyons View Pike Multiple Project Update
August 2, 2013 - Work continues to progress well within Zone 5 and along Lyons Pointe Lane. As soon as the disinfection and flushing processes are completed for the new water main on Lyons Pointe Lane, water services will be connected over to the new water main. Please continue to consult this blog on a regular basis as the Construction Progress Map will be updated frequently to track shifts in the full road closure area within Zone 5.
Schedule Note: At the current rate, KUB anticipates the project will be completed several weeks in advance of the original November time frame. We continue to work with the contractor and the City of Knoxville to further refine the original project completion date.
View Current Construction Progress Map for Zone 5
Backfilled trench in Zone 5
Fusing 50' sections of High Density Polyethylene sewer pipe
Schedule Note: At the current rate, KUB anticipates the project will be completed several weeks in advance of the original November time frame. We continue to work with the contractor and the City of Knoxville to further refine the original project completion date.
View Current Construction Progress Map for Zone 5
Backfilled trench in Zone 5
Fusing 50' sections of High Density Polyethylene sewer pipe
Thursday, August 1, 2013
Lyons View Project Update
July 31, 2013 Update – Construction Zone 5 Map updated. Please continue to consult this blog on a regular basis as the Construction Progress Map will be updated frequently to track shifts in the full road closure area within Zone 5.
View Current Construction Progress Map for Zone 5
View Current Construction Progress Map for Zone 5
Friday, July 26, 2013
Lyons View Project Update
July 26, 2013 Update - All work
in Zone 4 has been completed, and Blalock has now transitioned into Zone 5.
Within Zone 5, the trench that will contain the new utility lines will
transition from the north lane (westbound) to the south lane (eastbound) in the
vicinity of 5628 Lyons View Pike. In general, as placement of the new lines
within the trench is completed and the trench is backfilled, access to
individual driveways within Zone 5 will shift from Northshore Drive to Kingston
Pike as the trench work moves past each driveway.
Blalock has also begun working simultaneously in Lyons
Pointe Lane immediately to the east of Lyons View Pike. This work only affects
those residents that live along Lyons Pointe Lane.
Reminder: Access to all Cherokee Country
Club (CCC) facilities is only available from Kingston Pike. Access to CCC from
Northshore Drive will not be available until the project is completed.
Lyons View Pike remains closed to through traffic between
Lakeshore Park on the west end and Colony Way on the east end. Harley Drive
remains barricaded at the Lyons View Pike intersection for the duration of this
project.
Schedule Note: Although the weather has
been unusually wet through much of the project, the contractor has made good use
of the extended work hours, longer work week and multiple crews to make
excellent progress. As such, KUB is presently evaluating the remaining work and
coordinating with the contractor and the City to revise the anticipated
completion date. After the pipeline work is finished, the City's contractor will
complete the final paving of the road. Stay tuned to future updates for a
revised schedule on reopening Lyons View Pike to through traffic.
Preparing to mill the existing pavement in the eastbound lane
Common trench will contain new water, natural gas, and sewer for main pipes
Thursday, July 18, 2013
Lyons View Pike Project Update
July 18, 2013 Update - Work in Zone 3 has been completed. All traffic from address 5412 Lyons View Pike east must access from Kingston Pike. Blalock has completed the water main installation in Zone 4 and tied over all service lines. Work continues in Zone 4 to install the new sewer and natural gas mains. Barring any unforeseen construction issues, and weather permitting, Blalock expects to transition from Zone 4 to Zone 5 by next week.
Reminder: Access to all Cherokee Country Club (CCC) facilities is only available from Kingston Pike. Access to CCC from Northshore Drive will not be available until the project is completed.
Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Completion of the project is scheduled for November, 2013, prior to Thanksgiving.
View Current Construction Progress Map for Zone 4
Reminder: Access to all Cherokee Country Club (CCC) facilities is only available from Kingston Pike. Access to CCC from Northshore Drive will not be available until the project is completed.
Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Completion of the project is scheduled for November, 2013, prior to Thanksgiving.
View Current Construction Progress Map for Zone 4
Friday, July 12, 2013
Lyons View Pike Project Update
July 12, 2013 UPDATE -
Work on the far western end of Zone 3 is wrapping up as existing gas
services are being tied over to the new gas main. Installation of the
new water main within Zone 4 continues. Once the disinfection and
flushing process is complete on the new water main, the contractor will
begin tying water services over to the new water main. Customers will be
notified in advance of the brief interruption of water service as the
individual services are transferred to the new main. As soon as all
water main replacement work in Zone 4 is complete, Blalock will begin
work to replace the existing sewer and gas lines within Zone 4.
Note: The contractor will not be
working this Saturday & Sunday, July 13-14. The disinfection
process on the recently installed water line in Zone 4 is underway and
will not be ready for confirmatory sample collection and testing until
Monday morning, July 15. Work on other utilities in the area can't be
started until the new water line is in service, and the old water line
is removed, to make room for the other new utilities.
Reminder: Access to all Cherokee
Country Club (CCC) facilities is only available from Kingston Pike.
Access to CCC from Northshore Drive will not be available until the
project is completed.
Lyons View Pike remains closed to through traffic
between Lakeshore Park on the west end and Colony Way on the east end.
Harley Drive remains barricaded at the Lyons View Pike intersection for
the duration of this project. Completion of the project is scheduled for
November, 2013, prior to Thanksgiving.
Zone 4 Water Line Installation
Installing an isolation valve on existing 1915 6" Cast Iron Water Line
Wednesday, July 3, 2013
Lyons View Pike Project Update
July 3, 2013 UPDATE - Work in Zone 3 is nearing completion. By 3 p.m., Wednesday, July 3, placement of temporary pavement within the majority of Zone 3 will be complete. Blalock & Sons will adjust traffic control devices at 3 p.m. Wednesday such that all Cherokee Country Club (CCC) traffic must enter from and exit to Kingston Pike. After 3 p.m. Wednesday, July 3, all CCC facilities will not be accessible from Northshore Drive for the remainder of the project.
The construction contractors will not be working Thursday, July 4, through Sunday, July 7, and will resume activity on Monday, July 8. At that time, the remaining work on the western-most end of Zone 3 will continue, and preparation work for the new water line construction within Zone 4 will commence.
Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Completion of the project is scheduled for November, 2013, prior to Thanksgiving.
View Construction Progress Map Zone 4 (effective after 3 p.m., Wednesday, July 3)
The construction contractors will not be working Thursday, July 4, through Sunday, July 7, and will resume activity on Monday, July 8. At that time, the remaining work on the western-most end of Zone 3 will continue, and preparation work for the new water line construction within Zone 4 will commence.
Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Completion of the project is scheduled for November, 2013, prior to Thanksgiving.
View Construction Progress Map Zone 4 (effective after 3 p.m., Wednesday, July 3)
Thursday, June 27, 2013
June 27, 2013 UPDATE - Blalock & Sons has placed the new water line in Zone 3 into service and is tranferring all water services over to the new main. As work prepares to transition from water line construction to sewer and gas line construction in Zone 3, it is very important to stay abreast of the upcoming traffic changes for all vehicles wanting to reach Cherokee Country Club (CCC) facilities on the north side of Lyons View Pike (golf, tennis, swimming).
The schedule will be as follows:
Thursday, June 27, to Sunday morning, June 30, 8 a.m.
Access to CCC north side facilities from Kingston Pike ONLY
Sunday morning, June 30, 8 a.m., to Wednesday evening, July 3, 5 p.m.
Access to CCC north side facilities from Northshore Drive ONLY
Wednesday evening, July 3, 5 p.m., to Final Project Completion
Access to CCC north side facilities from Kingston Pike ONLY
Access to the CCC facilties on the south side of Lyons View Pike is unaffected, and will remain from Kingston Pike ONLY for the remainder of the project.
The construction contractors will not be working Thursday, July 4, through Sunday, July 7, and will resume activity on Monday, July 8. At that time, Zone 3 activity on the sewer and gas line replacements will be nearing completion, and preparations will begin for transitioning into Zone 4.
Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Completion of the project is scheduled for November, 2013, prior to Thanksgiving.
View Construction Progress Map Zone 3 (effective until 8 a.m., Sunday, June 30).
View Construction Progress Map Zone 3 (effective after 8 a.m., Sunday, June 30).
Construction activity and road barricade in Zone 3 west of Cherokee Country Club (from Kingston Pike).
Construction activity and road barricade from west end of project (from Northshore Drive).
The schedule will be as follows:
Thursday, June 27, to Sunday morning, June 30, 8 a.m.
Access to CCC north side facilities from Kingston Pike ONLY
Sunday morning, June 30, 8 a.m., to Wednesday evening, July 3, 5 p.m.
Access to CCC north side facilities from Northshore Drive ONLY
Wednesday evening, July 3, 5 p.m., to Final Project Completion
Access to CCC north side facilities from Kingston Pike ONLY
Access to the CCC facilties on the south side of Lyons View Pike is unaffected, and will remain from Kingston Pike ONLY for the remainder of the project.
The construction contractors will not be working Thursday, July 4, through Sunday, July 7, and will resume activity on Monday, July 8. At that time, Zone 3 activity on the sewer and gas line replacements will be nearing completion, and preparations will begin for transitioning into Zone 4.
Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Completion of the project is scheduled for November, 2013, prior to Thanksgiving.
View Construction Progress Map Zone 3 (effective until 8 a.m., Sunday, June 30).
View Construction Progress Map Zone 3 (effective after 8 a.m., Sunday, June 30).
Construction activity and road barricade in Zone 3 west of Cherokee Country Club (from Kingston Pike).
Construction activity and road barricade from west end of project (from Northshore Drive).
Thursday, June 20, 2013
June 20, 2013 UPDATE - All Cherokee Country Club (CCC) facilities (both north and south side of Lyons View Pike) are temporarily accessible from Kingston Pike ONLY. This is a temporary situation while crews install the new water line to the west. Please continue to consult this blog on a regular basis prior to driving to CCC to ensure access points have not changed.
Blalock & Sons continue to work in Construction Zone 3 installing the new water line. Once the water line is placed into service and water service lines tied over to the new main, the existing 98-year old cast iron water main will be removed to allow for installation of the new sewer and gas mains.
Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Completion of the project is scheduled for November 2013, prior to Thanksgiving.
View Current Construction Progress Map Zone-3
Blalock & Sons continue to work in Construction Zone 3 installing the new water line. Once the water line is placed into service and water service lines tied over to the new main, the existing 98-year old cast iron water main will be removed to allow for installation of the new sewer and gas mains.
Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Completion of the project is scheduled for November 2013, prior to Thanksgiving.
View Current Construction Progress Map Zone-3
Monday, June 17, 2013
June 17, 2013 UPDATE NOTE: Cherokee Country Club - Effective Monday evening, June 17, 2013, by 9 p.m., all Cherokee Country Club (CCC) facilities (both north and south side of Lyons View Pike) will only be accessible from the east end (Kingston Pike). This is a temporary change for those CCC members/guests accessing the north side (golf, tennis, swimming). This change will last for approximately 5-7 days while crews install the new water line to the west.
Please continue to consult this blog on a regular basis prior to driving to CCC to ensure access points have not changed.
View Current Construction Progress Map.
Please continue to consult this blog on a regular basis prior to driving to CCC to ensure access points have not changed.
View Current Construction Progress Map.
Wednesday, June 12, 2013
Lyons View Pike Multiple Utility Project Update
June 12, 2013 UPDATE - Work in Zone 2 has been completed, and Zone 3 work has started. The current construction zone runs from the west end of Cherokee Country Club (CCC) west to address 5404 Lyons View Pike. Blalock & Sons has begun installation of the new water line in Zone 3. Installation of the sanitary sewer and natural gas lines will follow.
The Construction Progress Map for Zone 3 is effective as of 1 p.m. on Wednesday, June 12, 2013.
Important Note: Effective immediately, the Cherokee Country Club facilities (club and main parking lot) on the south side of Lyons View Pike (LVP) are only accessible from the east end (Kingston Pike). CCC facilities (golf course, swimming pool, and tennis courts) on the north side of LVP will continue to be accessible from the west end (Northshore Drive) only until all construction activities move fully to the west of all CCC facilities.
Residences east of CCC remain accessible from the east while residences west of CCC remain accessible from the west.
View Current Construction Progress Map
The Construction Progress Map for Zone 3 is effective as of 1 p.m. on Wednesday, June 12, 2013.
Important Note: Effective immediately, the Cherokee Country Club facilities (club and main parking lot) on the south side of Lyons View Pike (LVP) are only accessible from the east end (Kingston Pike). CCC facilities (golf course, swimming pool, and tennis courts) on the north side of LVP will continue to be accessible from the west end (Northshore Drive) only until all construction activities move fully to the west of all CCC facilities.
Residences east of CCC remain accessible from the east while residences west of CCC remain accessible from the west.
View Current Construction Progress Map
Friday, June 7, 2013
Lyons View Pike Multiple Utility Project Update
June 7, 2013 UPDATE - Work in Construction Zone 2 is nearing completion, and Zone 3 work is set to begin. Blalock & Sons and Pipeline Construction are continuing with work immediately in front of Cherokee Country Club (CCC). Construction crews are in the process of connecting to the new water, sewer, and natural gas pipes already installed beneath the CCC golf cart tunnel. Blalock has completed preparation work related to resuming trench excavation activities for the new water line immediately west of CCC.
The current Construction Progress Map for Zone 2 has been updated to reflect the location of the Full Road Closure presently in place directly in front of CCC.
Important Note: The Cherokee Country Club facilities (club, main parking lot) on the south side of Lyons View Pike (LVP) remain accessible from both the east end (Kingston Pike) and west end (Northshore Drive). However, effective Wednesday, June 12, the Cherokee Country Club facilities (club, main parking lot) on the south side of Lyons View Pike (LVP) will only be accessible from the east (Kingston Pike). CCC facilities located on the north side of LVP (golf course, swimming pool, tennis courts) will continue to be accessible from the west end only until all construction activities move fully to the west of all CCC facilities.
The Construction Progress Map for Zone 3 will become effective on Wednesday, June 12.
All residences east of CCC continue to be accessible from the east end only. All residences west of CCC are accessible from the west end only.
Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Completion of the project is scheduled for November 2013, prior to Thanksgiving.
Construction Progress Map(s):
Current Zone 2 Map
Projected Zone 3 Map (effective Wednesday, June 12)
Construction immediately in front of Cherokee Country Club
Connecting new water, sewer, and gas mains to new lines previously installed beneath the Cherokee Country Club golf cart tunnel
Preparing for water line trench excavation west of Cherokee Country Club
The current Construction Progress Map for Zone 2 has been updated to reflect the location of the Full Road Closure presently in place directly in front of CCC.
Important Note: The Cherokee Country Club facilities (club, main parking lot) on the south side of Lyons View Pike (LVP) remain accessible from both the east end (Kingston Pike) and west end (Northshore Drive). However, effective Wednesday, June 12, the Cherokee Country Club facilities (club, main parking lot) on the south side of Lyons View Pike (LVP) will only be accessible from the east (Kingston Pike). CCC facilities located on the north side of LVP (golf course, swimming pool, tennis courts) will continue to be accessible from the west end only until all construction activities move fully to the west of all CCC facilities.
The Construction Progress Map for Zone 3 will become effective on Wednesday, June 12.
All residences east of CCC continue to be accessible from the east end only. All residences west of CCC are accessible from the west end only.
Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Completion of the project is scheduled for November 2013, prior to Thanksgiving.
Construction Progress Map(s):
Current Zone 2 Map
Projected Zone 3 Map (effective Wednesday, June 12)
Construction immediately in front of Cherokee Country Club
Connecting new water, sewer, and gas mains to new lines previously installed beneath the Cherokee Country Club golf cart tunnel
Preparing for water line trench excavation west of Cherokee Country Club
Friday, May 31, 2013
Lyons View Multiple Utility Project Update
May 31, 2013 UPDATE - Work in Construction Zone 2 continues. Blalock & Sons and Pipeline Construction are finishing up the new sewer and natural gas mains to the east of Cherokee Country Club (CCC), and will soon be connecting to the new sewer and natural gas pipes already installed beneath the golf cart tunnel. Blalock is also making preparations to resume water line installation work in front of CCC, and proceed west with the new water line.
The Construction Progress Map has been updated to reflect the new location of the full road closure.
Lyons View Pike remains close to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Cherokee Country Club access continues to be from the west end (Northshore Drive) only All residences east of CCC are accessible from the east end (Kingston Pike) only.
Completion of the project is scheduled for November 2013, prior to Thanksgiving.
View Current Construction Progress Map.
New sewer and natural gas mains being installed just east of Cherokee Country Club:
The Construction Progress Map has been updated to reflect the new location of the full road closure.
Lyons View Pike remains close to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Cherokee Country Club access continues to be from the west end (Northshore Drive) only All residences east of CCC are accessible from the east end (Kingston Pike) only.
Completion of the project is scheduled for November 2013, prior to Thanksgiving.
View Current Construction Progress Map.
New sewer and natural gas mains being installed just east of Cherokee Country Club:
Thursday, May 23, 2013
Lyons View Multiple Utility Project Update
May 23, 2013 UPDATE - Work continues in Construction Zone 2. Blalock & Sons, the general contractor, is laying new sewer and gas mains. Pipeline Construction, the sub-contractor, has completed installation of new gas, sewer, and water lines via directional bore beneath the golf cart tunnel in front of Cherokee Country Club.
NOTE: No work will be performed between Sunday evening, May 26, and Tuesday morning, May 28, in observance of Memorial Day on Monday, May 27, 2013.
Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Cherokee Country Club access continues to be from the west end (Northshore Drive) only. The Lyons Head development is now accessible from the east end (Kingston Pike) only.
Completion of the project is scheduled for November 2013, prior to Thanksgiving.
View Current Construction Progress Map
Zone 1 re-opened east of Colony Way
Installing water line beneath tunnel via directional bore
Fusing joints of high-density polyethylene (HDPE) sewer pipe
Open trench excavation for installing sewer and gas pipe
NOTE: No work will be performed between Sunday evening, May 26, and Tuesday morning, May 28, in observance of Memorial Day on Monday, May 27, 2013.
Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Cherokee Country Club access continues to be from the west end (Northshore Drive) only. The Lyons Head development is now accessible from the east end (Kingston Pike) only.
Completion of the project is scheduled for November 2013, prior to Thanksgiving.
View Current Construction Progress Map
Zone 1 re-opened east of Colony Way
Installing water line beneath tunnel via directional bore
Fusing joints of high-density polyethylene (HDPE) sewer pipe
Open trench excavation for installing sewer and gas pipe
Thursday, May 16, 2013
May 15, 2013 UPDATE - Restoration work on Construction Zone 1 is complete. The east end of Lyons View Pike between Kingston Pike and the intersections of Arrowhead Trail and Colony Way has been re-opened. However, the remainder of Lyons View Pike remains closed to through traffic west of Colony Way.
Construction work is underway within Zone 2. The construction progress map has been updated.
View Current Construction Progress Map
Construction work is underway within Zone 2. The construction progress map has been updated.
View Current Construction Progress Map
Thursday, May 9, 2013
Lyons View Multiple Utility Project Update
May 9, 2013 UPDATE - Installation of the water and natural gas mains is nearing completion in Construction Zone 1 (east end of the project). Individual water and natural gas service lines are being connected to the newly installed mains, and the roadway is being restored. Weather permitting, KUB anticipates re-opening the east end of Lyons View Pike to Colony Way the week of May 13. At that time, the Arrowhead Trail and Colony Way intersections with Lyons View Pike will also be opened. However, Lyons View Pike will remain closed to through traffic west of the intersection of Lyons View Pike and Colony Way. KUB will update the construction progress map and issue a notice prior to this section re-opening.
As Zone 1 work is wrapping up, Blalock has begun preliminary work within Construction Zone 2. Zone 2 will be approximately 2,000 feet in length, extending from just west of Colony Way all the way to Cherokee Country Club. Zone 2 will only involve the installation of sewer and natural gas mains. The existing 12" water line in Zone 2 was installed in 1995 and does not need to be replaced at this time. As a result, KUB anticipates Zone 2 construction will proceed quickly, and lengthening the work zone will help expedite the work. Extending Zone 2 also allows the contractor to begin the installation of sewer, water, and gas lines beneath the golf cart tunnel at Cherokee Country Club.
As work progresses within Zone 2, access for individual property owners will depend on where their driveway is in relation to the immediate trench work construction. Generally, if the active trench work is east of a driveway, the resident's access will continue to be from the west. Once the active trench work moves west of a driveway, their access should shift to the east. Since the utility work can progress fairly quickly and field conditions change rapidly at times, inspection personnel and field representatives will work closely with individual property owners to communicate and coordiate this information.
Lyons View Pike remains closed to through traffic for the remainder of the project. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Cherokee Country Club access continues to be from the west end (Northshore Drive). Completion of the project is scheduled for November 2013, prior to Thanksgiving.
Road Milling Equipment
Natural Gas Main Installation in Zone 1
Sewer Main Installation in Zone 1
As Zone 1 work is wrapping up, Blalock has begun preliminary work within Construction Zone 2. Zone 2 will be approximately 2,000 feet in length, extending from just west of Colony Way all the way to Cherokee Country Club. Zone 2 will only involve the installation of sewer and natural gas mains. The existing 12" water line in Zone 2 was installed in 1995 and does not need to be replaced at this time. As a result, KUB anticipates Zone 2 construction will proceed quickly, and lengthening the work zone will help expedite the work. Extending Zone 2 also allows the contractor to begin the installation of sewer, water, and gas lines beneath the golf cart tunnel at Cherokee Country Club.
As work progresses within Zone 2, access for individual property owners will depend on where their driveway is in relation to the immediate trench work construction. Generally, if the active trench work is east of a driveway, the resident's access will continue to be from the west. Once the active trench work moves west of a driveway, their access should shift to the east. Since the utility work can progress fairly quickly and field conditions change rapidly at times, inspection personnel and field representatives will work closely with individual property owners to communicate and coordiate this information.
Lyons View Pike remains closed to through traffic for the remainder of the project. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Cherokee Country Club access continues to be from the west end (Northshore Drive). Completion of the project is scheduled for November 2013, prior to Thanksgiving.
Road Milling Equipment
Natural Gas Main Installation in Zone 1
Sewer Main Installation in Zone 1
Tuesday, April 30, 2013
Lyons View Multiple Utility Project Week Two Update
April 30, 2013 UPDATE - KUB and contractor Charles Blalock and Sons continued work this past week on the multiple utility construction project along Lyons View Pike. Installation of the eight-inch sewer force main has been completed in Construction Zone 1 (east end of project). Blalock and Sons, and subcontractor Pipeline Construction, have begun excavation and installation of water and natural gas mains in Construction Zone 1 this week. Pipeline Construction successfully completed a test bore underneath the tunnel connecting the Cherokee Country Club parking lot and golf course on April 29, No rock was encountered beneath the tunnel during this test bore, which means that the contractor should be able to install pipelines via a bore method, thereby minimizing excavation and expediting work in that area. Lyons View Pike remains closed to through traffic for the remainder of the project. Completion is scheduled for November 2013, prior to Thanksgiving. Additionally, the Arrowhead Trail and Colony Way intersections with Lyons View Pike remain barricaded while construction is completed on the east end in Construction Zone 1. Harley Drive will remain barricaded at the Lyons View Pike intersection for the duration of this project. All local traffic entering and exiting Lyons View Pike must continue to do so from the west end, at the Northshore Drive intersection.
Friday, April 26, 2013
Blalock Not Working Saturday, April 27, Due to Weather Conditions
April 26, 2013 - The contractor, Charles Blalock & Sons, will not be working on Saturday, April 27. In anticipation of the inclement weather predicted for Saturday, Blalock worked during the early morning hours of Thursday, April 25, and continues to make preparations for critical tie-in work to be performed this Sunday, April 28. Placing the new line in service will allow Blalock to begin work on the water and gas line replacements in Zone 1 on Monday morning, April 29. As has been the case since construction began, there will be two crews on the job to ensure that work stays on schedule. Also scheduled for Monday, Pipeline Constrution Company will be conducting a one-day test bore beneath the golf cart tunnel in front of Cherokee Country Club to confirm sub-surface conditions.
Wednesday, April 24, 2013
Planned Temporary Water Service Interruption at East End of Lyons View Pike from 3-7 a.m. on April 25
April 24, 2013 - Early Thursday morning, April 25, between 3-7 a.m., KUB will be shutting down the section of water pipe in the Lyons View Pike Construction Zone 1 (area east of Arrowhead Trail) to allow the contractor, Blalock & Sons, to remove a short section of the water line that is in conflict with the new utilities to be installed. Customers affected by this water service outage have been notified. Other water customers in close proximity to the work, but not in the construction zone, may notice air bubbles in their water after the work is performed. Diffused air bubbles may cause the water to have a white appearance, but it goes away quickly as the air dissipates from the line. Allowing your water faucets to run for usually less than a minute should clear any trapped air from your plumbing. Please call KUB at 524-2911 if you have questions related to this temporary water service interruption. Please call 558-2330 for all other matters related to the Lyons View Pike project.
Tuesday, April 23, 2013
Week One Completed on Lyons View Multiple Utility Project
April 22, 2013 - KUB and contractor Charles Blalock and Sons are one week into the multiple utility construction project along Lyons View Pike. The traffic control plan was implemented as of April 15, 2013, and Lyons View Pike will remain closed to through traffic for the remainder of the project. Completion is scheduled for November 2013, prior to Thanksgiving. Additionally, the Arrowhead Trail and Colony Way intersections with Lyons View Pike remain barricaded while construction is completed on the east end of the work zone. Harley Drive will remain barricaded at the Lyons View Pike intersection for the duration of this project. All local traffic entering and exiting Lyons View Pike must do so from the west end, at the Northshore Drive intersection.
In addition to implementing the traffic control plan and barricades, Charles Blalock and Sons installed sediment and erosion control devices, completed the materials staging area across from Oak Grove Lane, and began excavation and installation of the sewer force main. Work on the water, and possibly natural gas lines, will begin within the next week.
Current Project Information Sheet & Construction Progress Map
Traffic control barricades in place on the east and west ends of the Lyons View Pike Project work zone
In addition to implementing the traffic control plan and barricades, Charles Blalock and Sons installed sediment and erosion control devices, completed the materials staging area across from Oak Grove Lane, and began excavation and installation of the sewer force main. Work on the water, and possibly natural gas lines, will begin within the next week.
Current Project Information Sheet & Construction Progress Map
Traffic control barricades in place on the east and west ends of the Lyons View Pike Project work zone
Tuesday, April 16, 2013
Lyons View Pike Project and Road Closure Begins
April 15, 2013 - KUB and its contractor, Charles Blalock and Sons, have started construction on the east end of Lyons View Pike, near the Kingston Pike intersection. Due to excavation in the roadway, and the ongoing presence of equipment, only local traffic will be permitted to travel in the construction zone. All local traffic entering and exiting Lyons View Pike must do so from the west end, at the Northshore Drive intersection. As a reminder, the entire construction zone limits on a 1.5 mile section of Lyons View Pike will remain closed to through traffic as the natural gas, water, and wastewater mains are upgraded in along this stretch of roadway. The closure of this section of Lyons View Pike will remain in effect for the duration of the project, which KUB anticipates will be completed in November 2013, prior to Thanskgiving.
News Release - Lyons View Pike Construction Project and Road Closure Underway
Current Project Information Sheet/Construction Progress Map
Crews placed traffic control devices and signage as the KUB multiple utility upgrade project began Monday, April 15, on Lyons View Pike.
News Release - Lyons View Pike Construction Project and Road Closure Underway
Current Project Information Sheet/Construction Progress Map
Crews placed traffic control devices and signage as the KUB multiple utility upgrade project began Monday, April 15, on Lyons View Pike.
Wednesday, April 10, 2013
Lyons View Pike Project and Road Closure Set to Begin on Monday, April 15
April 10, 2013 - As a reminder, KUB and its contractor, Charles Blalock and Sons, will close the entire construction zone limits on a 1.5 mile section of Lyons View Pike to through traffic starting at 7 a.m. on Monday, April 15, 2013, to coincide with the start of construction on a project to upgrade the natural gas, water, and wastewater mains in the area. The closure of this section of Lyons View Pike will remain in effect for the duration of the project, which KUB anticipates will be completed in November 2013, prior to Thanksgiving.
News Release/Updated Project Information Sheet and Map
News Release/Updated Project Information Sheet and Map
Tuesday, April 2, 2013
Electronic Message Boards Provide Project Updates
April 2, 2013 - In preparation for the April 15 start date for the multiple utility construction project along Lyons View Pike, KUB has installed electronic message boards at both the east and west ends of the construction zone to familiarize commuters with the pending road closure and project dates.
News Release - KUB Places Message Boards Ahead of Lyons View Pike Construction Project
Message board posted on the east end of the construction zone.
Message board posted on the west end of the construction zone.
News Release - KUB Places Message Boards Ahead of Lyons View Pike Construction Project
Message board posted on the east end of the construction zone.
Message board posted on the west end of the construction zone.
Friday, March 22, 2013
Project Update
March 22, 2013 - Following a second public meeting on March 21, KUB and its contractor, Charles Blalock and Sons, are currently mobilizing and finalizing preparations to begin construction on the Lyons View Pike multiple utility upgrade project in mid-April. The closure of Lyons View Pike to through traffic will coincide with the start of construction, and will remain in effect until the scheduled project completion date in November 2013.
See the attached information sheet for the updated project information.
See the attached information sheet for the updated project information.
Monday, March 11, 2013
Second Public Meeting for Lyons View Pike Project
What: Public meeting regarding the Lyons View Pike multiple utility construction project
Where: Bearden Elementary School Gymnasium, 5717 Kingston Pike
When: Thursday, March 21, at 6 p.m.
Who: Representatives from KUB's Engineering and Customer Support departments, prospective
contractor, and City of Knoxville Engineering
Where: Bearden Elementary School Gymnasium, 5717 Kingston Pike
When: Thursday, March 21, at 6 p.m.
Who: Representatives from KUB's Engineering and Customer Support departments, prospective
contractor, and City of Knoxville Engineering
Friday, March 1, 2013
Project Update
March 1, 2013 - KUB has issued bids for the project, and will select a contractor by mid March. Additionally, KUB’s utility locating contractor, USIC Locating Services, is scheduled to be working along Lyons View Pike over the next several days (weather permitting) to apply paint markings on the roadway and in easements to identify current underground utility locations to assist prospective bidders as they prepare their bids. The new utility lines installed as part of this project may not be placed in the same location as existing facilities. Motorists are advised that there may be temporary lane reductions in the immediate work area as USIC progresses along Lyons View Pike.
Lyons View Pike Pre-Construction Photos
Lyons View Pike westbound, approaching Arrowhead Trail and Colony Way
Lyons View Pike, near Lyons Head
Lyons View Pike eastbound, approaching entrance to Cherokee Country ClubThursday, February 7, 2013
Project Update
February 7, 2013 - The input from the public meeting on January 24 and the questionnaires showed that most customers preferred an extended work week and hours to allow quicker project completion. Some customers were interested in sharing the cost for underground electric; and others said they might be interested, depending on the cost. Underground electric service will not proceed unless customers decide to fund it.
Based on that input, KUB plans to ask contractors to bid on the Lyons View Pike construction project with instructions to:
- Provide firm bids for underground electric.
- Base bids on working 12 to 14 hours a day, seven days a week, weather permitting.
- Meet the construction time frame of April through fall of 2013.
After selecting a contractor, KUB will follow up with residents who were interested in underground electric service to determine whether to move forward. KUB will also provide additional information about the start of construction.
Have questions? Call the Lyons View Pike project hotline at 558-2330.
Tuesday, January 22, 2013
Public Meeting Information for Lyons View Pike
What: Public meeting regarding the Lyons View Pike utility construction project
Where: Sacred Heart Cathedral School Library, 711 Northshore Drive
When: Thursday, January 24, from 6 - 7:30 p.m.
Who: Representatives from KUB's Engineering and Customer Support departments
News Release - KUB to Host Public Meeting for Lyons View Pike Construction Project
Where: Sacred Heart Cathedral School Library, 711 Northshore Drive
When: Thursday, January 24, from 6 - 7:30 p.m.
Who: Representatives from KUB's Engineering and Customer Support departments
News Release - KUB to Host Public Meeting for Lyons View Pike Construction Project
Thursday, January 17, 2013
Lyons View Pike Project Information Sheet
For more information about the upcoming major utility construction project in the Lyons View Pike area, see the attached information sheet.
Subscribe to:
Posts (Atom)









