Friday, August 23, 2013

Lyons View Pike Project Update

August 23, 2013 - Work in Construction Zone 6 was completed on Thursday, August 22, with the placement of temporary pavement and general cleanup within the zone. Work in Zone 7 has already begun and will continue for approximately the next three weeks. Zone 7 is immediately southeast of Lyons View Pike and along the north boundary of Lakeshore Park. Installation of two new sewer mains in Zone 7 will require that construction equipment be located in Lyons View Pike for most of the next three weeks. Tree pruning and vegetation removal work continues along the entire route of Lyons View Pike. Motorists should continue to use caution when traveling through the area.

Traffic Note:  Effective Friday, August 23, the full road closure area will be located as shown on the updated Construction Progress Map for Zone 7. The road closure will remain at that location for the remainder of the project. All residences and businesses located west of the closure area will be accessible from Northshore Drive only. Those located east of the closure area will remain accessible from Kingston Pike only.

Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project.

No comments:

Post a Comment