Friday, July 12, 2013

Lyons View Pike Project Update

July 12, 2013 UPDATE - Work on the far western end of Zone 3 is wrapping up as existing gas services are being tied over to the new gas main. Installation of the new water main within Zone 4 continues. Once the disinfection and flushing process is complete on the new water main, the contractor will begin tying water services over to the new water main. Customers will be notified in advance of the brief interruption of water service as the individual services are transferred to the new main. As soon as all water main replacement work in Zone 4 is complete, Blalock will begin work to replace the existing sewer and gas lines within Zone 4.

Note: The contractor will not be working this Saturday & Sunday, July 13-14. The disinfection process on the recently installed water line in Zone 4 is underway and will not be ready for confirmatory sample collection and testing until Monday morning, July 15. Work on other utilities in the area can't be started until the new water line is in service, and the old water line is removed, to make room for the other new utilities.

Reminder: Access to all Cherokee Country Club (CCC) facilities is only available from Kingston Pike. Access to CCC from Northshore Drive will not be available until the project is completed.

Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end. Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project. Completion of the project is scheduled for November, 2013, prior to Thanksgiving.


Zone 4 Water Line Installation



 Installing an isolation valve on existing 1915 6" Cast Iron Water Line



Wednesday, July 3, 2013

Lyons View Pike Project Update

July 3, 2013 UPDATE - Work in Zone 3 is nearing completion. By 3 p.m., Wednesday, July 3, placement of temporary pavement within the majority of Zone 3 will be complete. Blalock & Sons will adjust traffic control devices at 3 p.m. Wednesday such that all Cherokee Country Club (CCC) traffic must enter from and exit to Kingston Pike. After 3 p.m. Wednesday, July 3, all CCC facilities will not be accessible from Northshore Drive for the remainder of the project.

The construction contractors will not be working Thursday, July 4, through Sunday, July 7, and will resume activity on Monday, July 8. At that time, the remaining work on the western-most end of Zone 3 will continue, and preparation work for the new water line construction within Zone 4 will commence.

Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end.  Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project.  Completion of the project is scheduled for November, 2013, prior to Thanksgiving. 
View Construction Progress Map Zone 4 (effective after 3 p.m., Wednesday, July 3)

Thursday, June 27, 2013

June 27, 2013 UPDATE - Blalock & Sons has placed the new water line in Zone 3 into service and is tranferring all water services over to the new main.  As work prepares to transition from water line construction to sewer and gas line construction in Zone 3, it is very important to stay abreast of the upcoming traffic changes for all vehicles wanting to reach Cherokee Country Club (CCC) facilities on the north side of Lyons View Pike (golf, tennis, swimming). 

The schedule will be as follows:

Thursday, June 27, to Sunday morning, June 30, 8 a.m.
Access to CCC north side facilities from Kingston Pike ONLY

Sunday morning, June 30, 8 a.m., to Wednesday evening, July 3, 5 p.m.
Access to CCC north side facilities from Northshore Drive ONLY

Wednesday evening, July 3, 5 p.m., to Final Project Completion
Access to CCC north side facilities from Kingston Pike ONLY

Access to the CCC facilties on the south side of Lyons View Pike is unaffected, and will remain from Kingston Pike ONLY for the remainder of the project. 

The construction contractors will not be working Thursday, July 4, through Sunday, July 7, and will resume activity on Monday, July 8.  At that time, Zone 3 activity on the sewer and gas line replacements will be nearing completion, and preparations will begin for transitioning into Zone 4. 

Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end.  Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project.  Completion of the project is scheduled for November, 2013, prior to Thanksgiving. 

View Construction Progress Map Zone 3 (effective until 8 a.m., Sunday, June 30). 

View Construction Progress Map Zone 3 (effective after 8 a.m., Sunday, June 30). 


Construction activity and road barricade in Zone 3 west of Cherokee Country Club (from Kingston Pike).





Construction activity and road barricade from west end of project (from Northshore Drive).


Thursday, June 20, 2013

June 20, 2013  UPDATE - All Cherokee Country Club (CCC) facilities (both north and south side of Lyons View Pike) are temporarily accessible from Kingston Pike ONLY. This is a temporary situation while crews install the new water line to the west. Please continue to consult this blog on a regular basis prior to driving to CCC to ensure access points have not changed.

Blalock & Sons continue to work in Construction Zone 3 installing the new water line. Once the water line is placed into service and water service lines tied over to the new main, the existing 98-year old cast iron water main will be removed to allow for installation of the new sewer and gas mains.

Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end.  Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project.  Completion of the project is scheduled for November 2013, prior to Thanksgiving.

View Current Construction Progress Map Zone-3

Monday, June 17, 2013

June 17, 2013  UPDATE NOTE:  Cherokee Country Club  - Effective Monday evening, June 17, 2013, by 9 p.m., all Cherokee Country Club (CCC) facilities (both north and south side of Lyons View Pike) will only be  accessible from the east end (Kingston Pike).  This is a temporary change for those CCC members/guests accessing the north side (golf, tennis, swimming).  This change will last for approximately 5-7 days while crews install the new water line to the west.

Please continue to consult this blog on a regular basis prior to driving to CCC to ensure access points have not changed.

View Current Construction Progress Map.

Wednesday, June 12, 2013

Lyons View Pike Multiple Utility Project Update

June 12, 2013 UPDATE - Work in Zone 2 has been completed, and Zone 3 work has started.  The current construction zone runs from the west end of Cherokee Country Club (CCC) west to address 5404 Lyons View Pike.  Blalock & Sons has begun installation of the new water line in Zone 3.  Installation of the sanitary sewer and natural gas lines will follow. 

The Construction Progress Map for Zone 3 is effective as of 1 p.m. on Wednesday, June 12, 2013. 

Important Note: Effective immediately, the Cherokee Country Club facilities (club and main parking lot) on the south side of Lyons View Pike (LVP) are only accessible from the east end (Kingston Pike).  CCC facilities (golf course, swimming pool, and tennis courts) on the north side of LVP will continue to be accessible from the west end (Northshore Drive) only until all construction activities move fully to the west of all CCC facilities. 

Residences east of CCC remain accessible from the east while residences west of CCC remain accessible from the west. 

View Current Construction Progress Map

Friday, June 7, 2013

Lyons View Pike Multiple Utility Project Update

June 7, 2013 UPDATE - Work in Construction Zone 2 is nearing completion, and Zone 3 work is set to begin.  Blalock & Sons and Pipeline Construction are continuing with work immediately in front of Cherokee Country Club (CCC).  Construction crews are in the process of connecting to the new water, sewer, and natural gas pipes already installed beneath the CCC golf cart tunnel.  Blalock has completed preparation work related to resuming trench excavation activities for the new water line immediately west of CCC. 

The current Construction Progress Map for Zone 2 has been updated to reflect the location of the Full Road Closure presently in place directly in front of CCC. 

Important Note: The Cherokee Country Club facilities (club, main parking lot) on the south side of Lyons View Pike (LVP) remain accessible from both the east end (Kingston Pike) and west end (Northshore Drive).  However, effective Wednesday, June 12, the Cherokee Country Club facilities (club, main parking lot) on the south side of Lyons View Pike (LVP) will only be accessible from the east (Kingston Pike).  CCC facilities located on the north side of LVP (golf course, swimming pool, tennis courts) will continue to be accessible from the west end only until all construction activities move fully to the west of all CCC facilities. 

The Construction Progress Map for Zone 3 will become effective on Wednesday, June 12. 

All residences east of CCC continue to be accessible from the east end only.  All residences west of CCC are accessible from the west end only. 

Lyons View Pike remains closed to through traffic between Lakeshore Park on the west end and Colony Way on the east end.  Harley Drive remains barricaded at the Lyons View Pike intersection for the duration of this project.  Completion of the project is scheduled for November 2013, prior to Thanksgiving. 


Construction Progress Map(s):

Current Zone 2 Map

Projected Zone 3 Map (effective Wednesday, June 12)


Construction immediately in front of Cherokee Country Club




Connecting new water, sewer, and gas mains to new lines previously installed beneath the Cherokee Country Club golf cart tunnel



Preparing for water line trench excavation west of Cherokee Country Club